A:
Standard Recycling Process (Clause 6.6.5):
1. Power-on unlocking: 36V voltage heating ≥ for 45min to melt the hot melt material (Fig. 2.1.1);
2. Mechanical cramping: special automatic recycling machine pulls out the steel strand, and manual pulling is prohibited;
3. Layered demolition: sequential operation from bottom to top, the width of the fertilizer trough ≥ 1.2m (clause 5.3.1).
Recovery failure plan (clause 6.6.6):
· casing drilling rig sleeve breaks the anchor solid;
· high-pressure water gun to release the formation bonding;
· The waterjet cuts off the bottom strand (suitable for extended bolts).